BWB were appointed as designers for diverting an existing HV cable route in the cess area from the top of an embankment between Wokingham and Bracknell stations. BWB were civil CRE (design) for the scheme
BWB attended site and undertook tape surveys creating offset points from existing structures. BWB ensured that the location of the diverted HV cable route was at least 2m from the nearest running rail, avoided any potential clash with existing services or infrastructure and was a safe distance from any falls negating the requirement for any retaining structures.