The Orion Building
Location: Birmingham
Services:
Sectors:
An iconic addition to Birmingham´s city centre skyline, opposite the Mailbox, the Orion Building with its impressive twenty six storey tower provided BWB with a number of significant engineering challenges.
The building will provide the bench-mark for luxury apartments for developer Crosby Homes, with phase two already having been commissioned.
Key engineering challenges on this project included:
- the construction of a deep basement adjacent to public highway and existing buildings
- high concentrations of vertical loading from the tower requiring the use of large diameter bored piles
- anti vibration mountings incorporated into the substructure due to the close proximity of the site to the main railway lines to New Street Station
- a vertical movement joint designed to accommodate thermal loads and differential movement between non-attenuated and attenuated elements, and to transfer lateral loads
- the retention and incorporation of a Victorian brick built façade requiring lateral restraint form the reinforced concrete flab slab frame and an ability to accommodate differential movement. Discharge of the section 278 agreement and a stage 1 and 2 safety audit

Head Office: 0115 9241100